You're in Safe Hands
Rigourous testing phase lead to fast and efficient implementation onsite
Client
Afton Lamella Plant
Location
Scotland
Service Provided Systems Integration
The Challenge
Total Automated Solutions won the contract to configure the Control and SCADA system on the new installation of a Lamella system at a Water Treatment Works in Scotland.
Waste Water Management
Installation of control, SCADA system and commissioning
Installed and fully operational in 5 days
The Solution
The system was installed to comply with Environmental guidelines on the waste water part of the plant, to keep the turbidity going back to the head of the works below a certain threshold
We successfully installed and fully commissioned the system onsite within five days. No revisits to site were needed due to the rigorous in house testing of the system that had been carried out in the workshop before delivery to site.
The Results
The customer was very happy and maintained that they had never commissioned a system so effortlessly, thanks to the work carried out prior to the site work.
Our Case Studies